Hi Sir
I am getting confused in the question below, can you please help me solve it
A chemical flavouring, product C is made by mixing two materials together:
Standard – Kg per batch – $ per kg – $ per batch
L – 300 – $1.30 – 390
H – 500 – $2.82 – 1,410
Input per batch 800kg
10% standard loss 80kg
Output per batch 720kg
For batch 1247 input as 250.5kg of L and 669.5kg of H. Output from the batch was 810kg of product C.
What is the yeild variance?
I am getting confused with the 10% loss part.
Thank you in advance!
ACCA Forums
PMYield Variance Question
For the yield variance compare the actual total input (920kg) with the standard total input for the actual production (810 x 800/720 = 900 kg), in both cases at standard mix (300/800 for L, and 500/800 for H) and at standard cost.
Have you watched my free lectures on mix and yield variances?
Sir, I got two different answers.
When I did it in Tabular form, I got the answer as 177.339 A
and when I did it this way (below) I got it as 45A.
920kg of Input Produced 810kg
920Kg of input should have produced 828kg
Yeild= 18x2.5 = 45A.
Please tell me where have I gone wrong.
Why are you attempting a question for which you do not have an answer? You should be using a Revision Kit from one of the ACCA Approved Publishers - they have answer :-)
I cannot tell you where you have gone wrong because I cannot see your workings to be able to check.
Again I ask, have you watched my free lectures on this?
Sir, I understood my mistake.
Sorry, for the trouble.
Thank you!
You are welcome :-)
This topic is locked — no new replies.
