- This topic has 1 reply, 2 voices, and was last updated 4 years ago by .
Viewing 2 posts - 1 through 2 (of 2 total)
Viewing 2 posts - 1 through 2 (of 2 total)
- The topic ‘variance help’ is closed to new replies.
Interactive BPP books for September 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › variance help
This question is according to example 6 (chapter 14) on ABC variance.
Is it true that total variance is calculated by taking total costs and divide them by total production units?
Total variance:
Actual overhead————————————————$126720
Standard overhead ($120000 / 48000) x 50400——-$126000
Variance———————————————————-$720
But in example 6 we are particularly asked Overhead expenditure and Overhead efficiency variances for despatches that means we have to calculate it by taking total overheads divided by total number of despatches (rather than total units).
This means that we have to calculate expenditure and efficiency variances based on a despatch basis (rather than total units basis).
Standard OH per despatch = $120000 / 2000 = $60 per depatch
OH expenditure variance:
Standard cost = $60 x 2200 despatch = $132000
Actual cost—–=—————————–= $126720
variance——–=——————————= $5280
OH efficiency variance:
Standard cost = $60 x 2200 despatch = $132000
Standard cost = $60 x 2100 despatch = $126000
variance——–=——————————= $6000
According to my understanding both the costs in the overhead efficiency variance is standard cost calculated using standard cost per despatch of $60. (is that right?)
Are my explanations and calculations correct?
They are correct, but I really do not know why you are asking because I work through the example in the lecture and the answer is also printed in the lecture notes!
