• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

ACCA December 2025 exams comments and polls >>

BPP Black Friday sale! (last day!)

40% discount on all BPP books specially for OpenTuition students!
Get it here >>

variance

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › variance

  • This topic has 1 reply, 2 voices, and was last updated 3 years ago by John Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • December 28, 2021 at 3:05 pm #644958
    maria2020
    Member
    • Topics: 18
    • Replies: 12
    • ☆

    You said that in all the cost variances we always compare actual cost vs standard cost with actual production valued at standard cost. We do not compare with the originally budgeted totals.

    Material Price:
    Total actual cost = actual kgs x actual cost per kg
    Total standard cost = actual kgs x standard cost per kg

    Material Usage:
    Total standard cost = actual kgs x standard cost per kg
    Total budget cost = standard kgs x standard cost per kg

    In the material price formula above we are comparing totals of actual cost and standard cost (just like you said we compare actual cost and standard cost). BUT the problem I have is with the material usage formula because we are comparing budget cost and standard cost in that variance like above (why is that?)

    December 28, 2021 at 5:31 pm #644970
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54797
    • ☆☆☆☆☆

    What you have written for the price variance is correct.

    What you have written for the usage variance is not correct.
    We compare the actual kgs with the standard kgs for the actual production, costing both of them at the standard cost per kg. (This is not the total budget cost at all).

    Have you watched the Paper MA lectures on variances as I suggested?

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • The topic ‘variance’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • John Moffat on Activity Based Costing part 2 – ACCA Performance Management (PM)
  • tjama on Totnes – ACCA SBR Question – Spreadsheet Exercise 3 – CF
  • Barroid on Activity Based Costing part 2 – ACCA Performance Management (PM)
  • mrjonbain on The nature and structure of organisations – ACCA Paper BT
  • unimkeabana on The nature and structure of organisations – ACCA Paper BT

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in