Sir,
(In the context of material usage variance:operational)
(R.SQ-A.SQ)
What would be the price to be multiplied with?
Revised standard price or
actual price
Sorry if it's a silly doubt
Ask the Tutor ACCA PM
Variance
The current examiner prefers that you use the original standard cost.
(Some people prefer using the revised standard cost and there is an argument for either. It gives a different answer but the examiner accepts either. I explain this in my free lectures and my lectures do it the way that the current examiner prefers, which is the easiest and quickest way as well :-) )
Sign into reply to this topic.