- This topic has 2 replies, 2 voices, and was last updated 9 years ago by .
Viewing 3 posts - 1 through 3 (of 3 total)
Viewing 3 posts - 1 through 3 (of 3 total)
- You must be logged in to reply to this topic.
Interactive BPP books for September 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › Variance
Question
Brake Ltd. manufactured and distributes brake discs to the automotive sector. The company operates an integrated standard cost system in which.
– Purchases of materials are recorded at standard cost
– Direct Material costs and direct labour costs are variable
– Production overheads are fixed and absorbed using direct labour hours.
Actual and budgeted data for May are shown below
– Budgeted direct materials per unit 0 2kg at $5/kg
– Direct Labour – 0.5/unit
– Budgeted production for the month was 10,000 units
– 22,500 kgs of materials were purchased
– The total standard cost of the materials was $115,000
-6000 direct labour hours were worked at a cost of $6/hour.
-Budgeted fixed production o/h in the period were $240000.
-Actual fixed production o/h in the period were $260000.
Variances calculated for may are as follows:
-material price variance $11250(A)
-labour efficiency variance $1750(A)
q-5: CALCULATE THE STANDARD RATE PER LABOUR HOUR.
(THE ANSWER SAYS $7, I can’t figure out how it comes down to $7. please help!)
Labour efficiency variance= (Ah-Sh) x Sr = 1750
= (6000-5750) X sr = 1750
sr>> 1750/250= $7.
Is my explanation correct Sir?
Yes – that is correct 🙂
