If i calculate the variance in these format, do i get full mark ? please advice
eg. efficiency and rate
SHSR(for actual prod)
efficiency –
AHSR
rate –
AHAR
I don’t understand your abbreviations!
For section A and B questions, nobody looks at your workings and so it does not matter how you do it.
For section C questions, it is the workings that get the marks rather than the final answer and so it is vital that it is clear to the marker what you are doing. Just writing something like AHSR will mean nothing to the marker.