VALUATION OF A PUT OPTION

SSHAWN4y ago
NOTE - I had asked a similar question previouly this one is different previous question was valuation of call option this i valuation of put option SCENARIO - Company X is a considering an investment in a joint venture to develop high quality office blocks to be let out to blue chip corporate clients. This project has a 30-year life, and is expected to cost Company X $90 million and to generate an NPV of $10 million for Company X. The project manager has argued that this understates the true value of the project because the NPV of $10 million ignores the option to sell Company X’s share in the project back to its partner for $40 million at any time during the first ten years of the project. The standard deviation is 45% p.a. and the risk-free rate is 5% p.a QUESTION identify the basic variables that are needed to complete the call option formula. Pa = PV of cash inflow Pe = cost of investment ANSWER IN THE TEXT Pa = 100m Assuming that this is in 10 years’ time, then 20 years of the project remain so Pa is estimated as 20/30 × 100 = $66.7m. Pe = 40m DOUBT 1) should't the cost of investment (Pe) be 90 million since they have invested 90m ? why is it 40 m 2) should't the PV of cash inflow (Pa) be 100 million since 90M+10M(NPV) ? how have they arrived at the figure 66.7M could you please explain in detail
John MoffatJohn MoffatTutor4y ago#1
1. Because the option is to be able to sell the project at a price of $40M (that is what it would be exercised for). 2. The PV of the cash inflows now is $100M. The answer you are quoting is using the PV in 10 years time, but there is no reason that the PV should fall linearly as they have assumed. I do not know where you found this question but I cannot believe this would be asked in a real exam question.
Sign in to reply to this topic.