Isn’t V model a part of quality issues which has been removed from P3 course. I think quality of software is also not included in either ebusiness or improving business process chapters. I think we can exclude those topics.
V model is not in the syllabus. I don’t believe it’s in our notes either.
Thanks
Sir, so most probably this question number 2 of December 2008 must be out of date.
(a) The project plan shows a number of planned activities. Explain how each of the following three activities
contribute to the testing and quality of the software for CaetInsure:
(i) System testing;
(ii) Acceptance testing;
(iii) Data migration. (9 marks)
(b) Evaluate the alternative strategies available to ASW’s project manager to address the slippage problem in
the CaetInsure project. (10 marks)
(c) As a result of your evaluation, recommend and justify your preferred solution to the slippage problem in the
CaetInsure project. (6 marks)
Am I right?
Part (a) is out of date. Parts (b) and (c) are fine as they are to do with project management.
I think the full question is out of date!