Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › unskilled labour cost
Sales (units) : 2000 (Aple) , 4500(Bola)
Production (units) : 1750 (Aple) , 5000 (Bola)
Labour :
Skilled at $10/hrs : 2hrs/unit (Aple) , 2hrs /unit (Bola)
Unskilled at $7/hrs : 3hrs /unit (Ape) , 4hrs /unit (Bola)
what is the budget cost for unskilled labour for the period? Answer is $176,750 ??
Yes – $176750 is correct.
Thanks 🙂 🙂 🙂
You are welcome 🙂
May you please explain how to arrive at that figure $176750
For each product, multiply the production units by the unskilled hours required.
Add them up, and then multiply by the rate per hour 🙂