Hi!
When calculating total factory costs for the throughput accounting ratio, do you include the direct labour costs?
I’ve seen some answers to questions that do and some that don’t?
I believe that you do!
Thanks,
Rob.
You are correct.
In throughput accounting labour is always classed as a fixed cost so needs to go together with other production overheads to make total factory costs.
Kind Regards