Hi John,
I am referring to Dec 14 F5 paper, question 2 in section B (Glam co.)
How should one understand in such a question whether the labour cost of all staff should be taken for factory cost calculation or just the bottleneck staff?
Thanks in advance.
Regards,
Nitin
We always take total factory costs – not just those in the bottleneck (just as when calculating the return per hour we take into account all material costs, not just those in the bottleneck).