- This topic has 1 reply, 2 voices, and was last updated 4 years ago by .
Viewing 2 posts - 1 through 2 (of 2 total)
Viewing 2 posts - 1 through 2 (of 2 total)
- You must be logged in to reply to this topic.
Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Throughput accounting..
Hello sir,
Sir I have conceptual doubt about bottleneck (process or resource)
Would it be right to call bottleneck resource as the slowing process rather than slowest process.
I.e should I determine the bottleneck by identifying the slowest process or should I take capacity also to consideration..
It may be a silly doubt sorry if though!
The bottleneck process is the process that is limited the number of units that can be produced – the process that is slowing everything else down.
Have you watched my free lectures on this?
