- March 27, 2019 at 8:31 pm #510639
If there is a bottleneck resource of 4000 hours and there are 3 products to be made. The first ranked and 2nd ranked products are made within 3000 hours leaving 1000 hours for rank 3 product. And the demand for product 3 is for example 300 units and it’s taking only 600 hours leaving 400 for nothing. what do we do in those 400 hours? if the demands are full filled for each product?. If the demands are full filled, is it to assume there is no bottleneck resource?
March 28, 2019 at 7:47 am #510675If there are no other products then they simply will not run the machine for the 400 hours that are not needed! (and effectively it ends up with there not being a bottleneck)
If this is an actual question you are quoting, then it does seem a bit strange for it to occur in an exam question – it makes me wonder if you have typed out all of the question correctly.
March 28, 2019 at 5:28 pm #510722No it wasn’t, I was just wondering “what if” the demands are satisfied. Thank you.
March 29, 2019 at 6:35 am #510756You are welcome 🙂