• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exams

How was your exam? Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

TARGET COSTING-EDWARD CO. DEC. 2007

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › TARGET COSTING-EDWARD CO. DEC. 2007

  • This topic has 11 replies, 5 voices, and was last updated 8 years ago by John Moffat.
Viewing 12 posts - 1 through 12 (of 12 total)
  • Author
    Posts
  • August 17, 2012 at 8:21 am #54177
    Tenuvi
    Member
    • Topics: 5
    • Replies: 9
    • ☆

    I will like to know why in arriving at the desired profit,margin was changed to mark up to arrive at the answer. In the question,it was stated that the board have agreed that the acceptable margin(after allowing for all production costs) should be 20% and it was also stated that selling price is $44. I think since margin is calculated on selling price, we could have just found 20% of $44, to arrive at our desired profit. Am a bit confused as to how it was treated in the solution. Please explain.

    August 17, 2012 at 6:10 pm #104416
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    What you have typed is correct.
    So…if the selling price is 44.00 and the desired profit is 20% x 44 = 8.80, then it means that the target cost is 44.00 – 8.80 = 35.20.
    This is the figure in the answer – “the desired cost = 35.20”
    We compare this with the estimated cost ( 35.928) and the difference is the cost gap.

    August 17, 2012 at 10:52 pm #104417
    Tenuvi
    Member
    • Topics: 5
    • Replies: 9
    • ☆

    Tanx a lot!

    August 18, 2012 at 1:24 pm #104418
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    You are welcome.

    August 18, 2012 at 1:25 pm #104419
    Anonymous
    Inactive
    • Topics: 0
    • Replies: 2
    • ☆

    @johnmoffat said:
    What you have typed is correct.
    So…if the selling price is 44.00 and the desired profit is 20% x 44 = 8.80, then it means that the target cost is 44.00 – 8.80 = 35.20.
    This is the figure in the answer – “the desired cost = 35.20”
    We compare this with the estimated cost ( 35.928) and the difference is the cost gap.

    If the selling price is 44 and the mark up is 20% then cost is 44/1.2= 36.67 and not 35.928.

    August 19, 2012 at 5:20 pm #104421
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    <cite>@ndachuwa said:</cite>
    If the selling price is 44 and the mark up is 20% then cost is 44/1.2= 36.67 and not 35.928.

    But the question makes no mention of a mark-up.

    It says a margin of 20%, and a margin is a percent of selling price.

    Also, I did not write that 35.928 is the target cost at all – it is the estimated actual cost.

    What I wrote above in answer to the previous question is completely correct!

    October 30, 2013 at 11:00 am #144124
    No way
    Member
    • Topics: 8
    • Replies: 26
    • ☆

    I feel a bit tricky while I calculate allowance for waste and idle time of this question. Why multiply by the factor 100/90 is more correctly. I calculate by adding more time/material to come to actual figure this way seem incorrect as examiner’s report. Please explain for me?

    October 31, 2013 at 3:49 pm #144228
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    The point is that for every 100 hours we pay for, only 90 hours are actually worked (because 10% of the hours paid are idle).

    Putting this the other way round, for every 90 hours we work we need to pay for 100 hours.

    So….if we work for (say) 180 hours then we need to pay for 200 hours (180 x 100/90)

    The same logic applies to the wire also.

    October 31, 2013 at 4:53 pm #144245
    No way
    Member
    • Topics: 8
    • Replies: 26
    • ☆

    I hv got this in otherway:
    Efficiency ratio = expected time(=0.5 hrs)/actual time = 90/100 => actual time = 0.5 hrs x 100/90.
    The same applies for the wire.

    Thanks in adv John Moffat!

    October 31, 2013 at 5:13 pm #144249
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    Err….I think its the same 🙂

    Anyway, as long as you are OK with it now that is all the matter 🙂

    February 10, 2017 at 5:05 am #371817
    anu1234
    Member
    • Topics: 78
    • Replies: 65
    • ☆☆

    I have got a doubt in the same question. Component 2 section. In arriving at cost per unit they have multiplied .25 *5 * (100/98) I understand they are taking into account of waste. But why multiply the wasted material. I dont get the logic

    February 10, 2017 at 7:00 pm #371883
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    For every 100 m that they buy, the lose 2 and therefore only 98 are available for production.

    Therefore for every 98 they need, they will have to buy 100.

  • Author
    Posts
Viewing 12 posts - 1 through 12 (of 12 total)
  • The topic ‘TARGET COSTING-EDWARD CO. DEC. 2007’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • John Moffat on MA Chapter 4 Questions Cost Classification and Behaviour
  • maryrena77 on The nature and structure of organisations – ACCA Paper BT
  • vi234 on MA Chapter 4 Questions Cost Classification and Behaviour
  • vi234 on MA Chapter 4 Questions Cost Classification and Behaviour
  • John Moffat on The financial management environment – ACCA Financial Management (FM)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in