- December 9, 2016 at 6:28 am #362508
1.Predicted SP is $56
Desired mark up 25%
Material cost is estimated to be $16 before allowing for additional materials to allow of shrinkage of 20%( for every 10 kg of material going in, only 8 kg comes out)
Labour is the only other cost and 2 hrs are needed.What is the most the business can pay per labour hour, if the cost gap is to be avoided?
-The answer is $12.40
-I do have obtained the target cost which is $44.8
-Could you briefly explain what does “shrinkage of 20%” mean in the context and how to deal with it.2. Are lectures available for “relevant cost analysis”?
Thanks.
December 9, 2016 at 7:17 am #3625341. Shrinkage is the same was wastage. Therefore to allow for the waste, they will actually need to pay 10/8 x $16 for materials.
2. Of course – there are lectures on everything. They are a complete free course covering everything needed to be able to pass the exam well.
December 9, 2016 at 8:43 am #362561Got the answer. Thank you
December 9, 2016 at 2:30 pm #362644You are welcome 🙂