Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › Standard Costing
- This topic has 3 replies, 2 voices, and was last updated 9 years ago by
John Moffat.
- AuthorPosts
- December 1, 2015 at 5:49 pm #286795
I am struggling on that question in Kaplan Exam Kit(Ques.236). Please guide me.
10,800 hours actually worked and paid costing $8,770.
If the rate variance is $706 adverse, the efficiency variance $256 favourable, and 5,000 units were produced, what is the standard production time per unit?Thank you
December 1, 2015 at 6:11 pm #286804Since the rate variance is 706 adverse, then they should have paid (at standard cost) a total of 8,770 – 706 = 8,064 for the hours actually worked.
That means that the standard rate per hour is 8,064 / 10,800 = $0.746666 per hour
Since the efficiency variance is 256 favourable, they must have worked 256 / 0.746666 = 342.86 hours less than they should have worked.
They actually worked for 10,800 hours, so the standard hours for the actual production must have been 10,800 + 342.86 = 11,142.86 hours.
This is for 5,000 units, so the standard time per unit = 11,142.86 / 5,000 = 2.23 hoursI am a bit worried because usually in exam question the answer come to more exact figures. Check that you have copied the question correctly (although even if you have mistyped a figure, the workings above should make sense).
December 1, 2015 at 6:51 pm #286818Thank you sir for your response.
In fact, i had really mistyped a figure. It was 10,080 hours instead of 10,800 hours.
The correct answer will then be 2.08.Thank you sir for your guidance.
December 2, 2015 at 7:31 am #286882You are welcome 🙂
- AuthorPosts
- You must be logged in to reply to this topic.