Hi all,
In the BPP Practice& Revision Kit page68, question 16.9, it counts the idle time labour cost
as part of the Direct Labour cost Budget, but I thought Idle time labour cost is considered
as indirect labour cost? It would be much appreciated if someone could explain this.
ACCA Forums
MAShould Idle time labour cost be counted as Direct Labour Cost Budget?
What makes the lab-our cost
1 Labour Hours themselves
2 The rate at which the hours are paid.
3 The hours expected that our employees wont be doing work (idle time)
According to the question The standard or budget says it takes 6 hrs to make to make a unit however 20% idle time.What this means is you as Management Accountant preparing a budget u know getting the product done will take employees 6 hrs however u know your employee will be probably chatting discussing their issues such that 6 hr job will end up taking 6 hrs +iddle time.As this is normal that means you have to pay them for the 6 hrs +idle time.
Note iddle time is not 20% of 6 .It is number hours that if we remove 20% we he get 6hrs