Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › ROI and priority
- This topic has 3 replies, 2 voices, and was last updated 7 years ago by John Moffat.
- AuthorPosts
- August 6, 2017 at 9:55 am #400719
Dear tutor, i found below question from kaplan exam kit.
Question:
The following information about the division of Grate Co is available as follows:
Risk environment Drvision X (low)
Revenue: $50,000
Operating cost: 20,500
Fixed cost: 11,000
Profit: 18500Capital empoyed: 150,000
Half of fied cost for the division is allocated head office expenses. Grate Co has a cost of capital of 15%
In order to try and improve the current performance, the manager of division X is considering 3 newprojects.
capital investment profit
project 1 48,000 12,000
project 2 100,000 22,000
project 3 50,000 9,000If the projects are ranked to their ROI, which project will be the priority choice for Division X?
The answer given is B project 2. I really don’t understand the workings given in the book. Please help me.
Below is the answer given:
ROI for project 1,2, 3 is 25%, 22% and 18% respectively. (calculate the ROI is not a problem for me)
Project 1+2
12000-48000 x > 22000-100,000x
52,000x>10,000
x>0.192Project 2+3
22,000-100,000x> 9,000-50,000x
13,000>50,000x
0.26>xMay I know why need to calculate the project 1+2 and 2+3? and what are the funtions for?
Thanks a lot:)
August 6, 2017 at 5:01 pm #400764Assuming that you have copied the question and answer correctly (I only have the BPP Revision Kit and so I cannot check for myself) then the answer makes absolutely no sense at all.
It looks more as though they are doing something to do with RI rather then ROI, but even then it makes no sense.
The priority choice using ROI is simply project 1.
Sorry 🙂
August 8, 2017 at 3:58 pm #401041I agree with you. Thank you so much
August 8, 2017 at 4:57 pm #401054You are very welcome 🙂
- AuthorPosts
- The topic ‘ROI and priority’ is closed to new replies.