RISK AND UNCERTAINTYForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA APM Exams › RISK AND UNCERTAINTYThis topic has 2 replies, 2 voices, and was last updated 3 years ago by Sienna30.Viewing 3 posts - 1 through 3 (of 3 total)AuthorPosts March 4, 2021 at 6:51 am #613210 Sienna30MemberTopics: 5Replies: 6☆in the exam, if you use the wrong term for example “maximum rule” instead of maximax rule but explain it well in that it is a risk seekers preferred decision making approach ……would the marker mark you down for describing it as the “maximum rule?” March 4, 2021 at 10:20 am #613275 Ken GarrettKeymasterTopics: 10Replies: 10544☆☆☆☆☆Personally, I wouldn’t deduct much, if anything. The principle is more important than the name. March 4, 2021 at 11:37 am #613288 Sienna30MemberTopics: 5Replies: 6☆Thank youAuthorPostsViewing 3 posts - 1 through 3 (of 3 total)The topic ‘RISK AND UNCERTAINTY’ is closed to new replies.