hie guys may someone please help. shouldn’t basic pay be $360? basic pay is $9/hour for a forty hour week. normal production in that time =120 units. bonus =50% of the time saved on production paid at time and third. what will be the total wage in a week in which 150 units are made in 40 hours?
answer basic pay=45*$9 = 405 150 units should take 50 hours 150 units took 40 hours hours saved 10 hours bonus=50%*10*9*4/3 =60 total pay =465