• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exam Results

Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for June 2025 exams.
Get your discount code >>

Relevant costs in project appraisal

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FM Exams › Relevant costs in project appraisal

  • This topic has 3 replies, 2 voices, and was last updated 8 years ago by John Moffat.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • May 3, 2017 at 6:28 pm #384765
    myacca1990
    Participant
    • Topics: 153
    • Replies: 164
    • ☆☆☆

    1) LW Co has a half empty factory on which it pays $5,000 pa rent. If it takes on a new project, it will have to move to a new bigger factory costing $17,000 pa and it could rent the old factory out for $3,000 pa until the end of the current lease.
    What is the rental cost to be included in the project appraisal?
    A $14,000
    B $17,000
    C $9,000
    D $19,000

    2)A new project being considered by BLW Co would require 1,000 hours of skilled labour. The current workforce is already fully employed but more workers can be hired in at a cost of $20 per hour. The current workers are paid $15 per hour on a project that earns a
    contribution of $10 per hour.
    What is the relevant cost of labour to be included in the project appraisal?
    A $10,000
    B $15,000
    C $20,000
    D $25,000

    Well these relevant costing questions have always been difficult for me.
    According to me the answer to question 2 should be B because relevant cost are lost contribution plus the cost of paying the extra rate to labor.But the correct answer is C.
    The answer of question no 1 is A because we have to take account of the extra amount we have to pay for taking a project.But why the same logic does not apply to question 2?
    Some explanation will be helpful.

    May 4, 2017 at 6:35 am #384788
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54704
    • ☆☆☆☆☆

    There is not really any connection between the two questions.

    For question 1, they will still be paying the 5,000 rent whatever happens and so this is not relevant.
    If they do the new project they will have to pay 17,000 a year, but will be able to receive 3,000 a year from renting out the existing factory.
    So a net relevant cost of 14,000.

    For question 2, if they use the current workforce then the cost will be $25 per hour (last contribution plus the labour cost). However, instead of using the current workforce, they have the option to leave the workers where they are and hire more workers at a cost of $20 per hour. It is cheaper to hire more workers and so that is what they will do, and therefore the relevant cost is $20 per hour.

    May 4, 2017 at 1:02 pm #384838
    myacca1990
    Participant
    • Topics: 153
    • Replies: 164
    • ☆☆☆

    I got it but they get tricky sometimes 🙂

    May 4, 2017 at 5:20 pm #384860
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54704
    • ☆☆☆☆☆

    They do indeed 🙂

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • The topic ‘Relevant costs in project appraisal’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • AdityaSairam on Overcapitalisation and Overtrading – ACCA Financial Management (FM)
  • verweijlisa on Financial performance – Example 2 – ACCA Financial Reporting (FR)
  • John Moffat on Linear Programming – Spare capacity and Shadow prices – ACCA Performance Management (PM)
  • John Moffat on The Statement of Financial Position and Income Statement (part d)
  • Salexy on Linear Programming – Spare capacity and Shadow prices – ACCA Performance Management (PM)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in