• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exams

How was your exam? Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

Relevant costs in DCF investment decisions

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FM Exams › Relevant costs in DCF investment decisions

  • This topic has 7 replies, 3 voices, and was last updated 10 years ago by John Moffat.
Viewing 8 posts - 1 through 8 (of 8 total)
  • Author
    Posts
  • May 24, 2015 at 2:11 pm #248416
    sarah
    Member
    • Topics: 14
    • Replies: 10
    • ☆

    Hello,

    I am a bit confused about which costs should be taken into account in investment appraisal, specifically regarding contribution and labour. I have seen one question answered by including both contribution foregone and the labour costs as cash outflows, and another question where only the lost contribution is taken into account. In both cases the workers would have been diverted from other work.

    Could you explain which it should be ? I think the former is right but then I really can’t understand how the other question I am looking at is correct.

    Thank you,

    May 24, 2015 at 5:54 pm #248504
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    The former is right, but without seeing the specific question it is impossible for me to explain why they have done differently (or to tell you they have made a mistake if that is the case).

    May 25, 2015 at 9:10 pm #248995
    sarah
    Member
    • Topics: 14
    • Replies: 10
    • ☆

    OK, I will revisit the question and have another go! thank you for clarifying.

    May 26, 2015 at 9:01 am #249069
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    You are welcome 🙂

    May 26, 2015 at 3:20 pm #249198
    Robert
    Member
    • Topics: 58
    • Replies: 175
    • ☆☆☆

    Hi john, sorry to gate crash this thread but my question is similar to Sarah’s.

    It’s regarding relevant costs:

    A new project would require 1000 hours of labour. The current workforce is already fully employed but more workers can be hired at a cost of $20 per hour.
    The current workers are paid $15 per hour on a project that earns $10 contribution.
    What is the relevant cost of labour?

    Bpp Answer: $20,000 ($20×1000 hours)

    This is part of bpp’s explanation which i don’t understand:
    Cost to divert existing labour =
    Lost contribution + labour cost ($10+$15 x1000 =$25000)

    My answer would have been $10,000x $15=€15000

    Would you mind telling me why we have to include the $10 per hour when calculating the above please?

    Thanks

    May 26, 2015 at 4:55 pm #249266
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    BPP are correct and I explain this in two different ways in the lecture.

    If the contribution is $10, then this is after charging labour of $10. So the amount earned (before labour) must be $25.

    If you move the labour to the contract, then you are still paying the $10 – so no difference there – but you will need to be earning $25 from the contract to replace the $25 from where they currently are.

    If you are not happy with this way of explaining, then you will have to watch the lecture where I explain it another way. Once you have got it then learn it as a rule – it is always cost of labour plus lost contribution in this sort of question.

    May 26, 2015 at 5:46 pm #249299
    Robert
    Member
    • Topics: 58
    • Replies: 175
    • ☆☆☆

    Thanks john

    May 27, 2015 at 7:23 am #249419
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    You are welcome 🙂

  • Author
    Posts
Viewing 8 posts - 1 through 8 (of 8 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • John Moffat on Activity Based Costing part 1 – ACCA Performance Management (PM)
  • Shabi on Activity Based Costing part 1 – ACCA Performance Management (PM)
  • Ark1 on Variance Analysis (part 4) – ACCA Management Accounting (MA)
  • EricObi on IAS 37 – Best estimate – ACCA Financial Reporting (FR)
  • Ken Garrett on The nature and structure of organisations – ACCA Paper BT

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in