• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

March 2026 ACCA Exams Results

Comments & Instant poll

Save 20% on ACCA & CIMA Books

Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>

Relevant costing (further processing)

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Relevant costing (further processing)

  • This topic has 4 replies, 2 voices, and was last updated 3 years ago by John Moffat.
Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • February 8, 2023 at 2:38 pm #678545
    youshaali
    Participant
    • Topics: 51
    • Replies: 87
    • ☆☆

    In a question company input 100 units and extract output of 60 units and variable cost incurred in the middle of the process so my question is whether we multiply variable cost by 100 units or 60 units ?

    (No information given about losses that when loss occurred in the process)

    February 8, 2023 at 3:26 pm #678551
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54835
    • ☆☆☆☆☆

    If there is no other information given in the question, then I would multiply by 100 units.

    What does the printed answer do?

    February 8, 2023 at 3:27 pm #678552
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54835
    • ☆☆☆☆☆

    If there is no other information given in the question, then I would multiply by 100 units.

    What does the printed answer do?

    February 8, 2023 at 6:10 pm #678560
    youshaali
    Participant
    • Topics: 51
    • Replies: 87
    • ☆☆

    Actually in the original question, variable cost incurred at start of the process so I thought what if we incurred this cost at middle of the process.
    Thank you sir for your answer!!!
    I was so confused….

    February 9, 2023 at 7:30 am #678596
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54835
    • ☆☆☆☆☆

    You are welcome 🙂

  • Author
    Posts
Viewing 5 posts - 1 through 5 (of 5 total)
  • The topic ‘Relevant costing (further processing)’ is closed to new replies.

Primary Sidebar

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE Exams – Instant Poll

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • mrjonbain on ACCA TX-UK FA2025 Chapter 3 Property Income and Investments – Individuals
  • mlkk2019 on ACCA TX-UK FA2025 Chapter 3 Property Income and Investments – Individuals
  • furat2@hotmail.com on Activity Based Costing part 1 – ACCA Performance Management (PM)
  • John Moffat on Financial management objectives – ACCA Financial Management (FM)
  • prathikr on Financial management objectives – ACCA Financial Management (FM)

Copyright © 2026 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in