AAndy6y ago
Bronty Co is considering whether to undertake some contract work for a customer. The machinery required for the contract would be as follows: A special cutting machine will have to be hired for three months for the work (the length of the contract). Hire charges for this machine are $75 per month, with a minimum hire charge of $300. Sir can you specify what will be the relevant cost in this case, and why exactly?
John MoffatJohn MoffatTutor6y ago#1
Why are you attempting questions for which you do not have an answer? You should be using a Revision Kit from one of the ACCA approved publishers - they have answers and explanations! The relevant cost is $300 because this is how much they would have to pay to hire the machine. Have you watched my free lectures on relevant costing?
AAndy6y ago#2
Sir why are $75 of monthly hire charges not considered relevant?
John MoffatJohn MoffatTutor6y ago#3
Because they have to pay $300 which is the minimum they will be charged (and is more than 3 months at $75 per month).
Sign into reply to this topic.