• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Relevant Costing

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Relevant Costing

  • This topic has 7 replies, 4 voices, and was last updated 9 years ago by John Moffat.
Viewing 8 posts - 1 through 8 (of 8 total)
  • Author
    Posts
  • September 8, 2015 at 5:02 pm #270468
    Debajyoti
    Member
    • Topics: 8
    • Replies: 7
    • ☆

    Q) A contract requires 100 hours of skilled labour. Labour is paid $5 per hour. Labour is fully occupied making another product which is generrating a contribution 0f $8 per unit. Each unit of the other product requires 2 hours of skilled labour. What is the relevant cost of labopur?

    Would appreciate your help in anvance.

    September 8, 2015 at 5:19 pm #270474
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54656
    • ☆☆☆☆☆

    Each unit of the other product lost is losing us $8 + (2 hours x $5) = $18.
    Each unit takes 2 hours, so it is losing 18/2 = $9 per hour.

    The contract needs 100 hours, so the relevant cost is 100 x 9 = $900

    September 8, 2015 at 5:39 pm #270483
    Debajyoti
    Member
    • Topics: 8
    • Replies: 7
    • ☆

    Thanks.

    September 8, 2015 at 7:18 pm #270513
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54656
    • ☆☆☆☆☆

    You are welcome 🙂

    September 16, 2015 at 9:55 pm #272215
    Noureen
    Participant
    • Topics: 14
    • Replies: 16
    • ☆

    Hi john,

    I’m doing a question about relevant costing and the question say that you are the management accountant of a publishing and printing company which has been asked to quote for the production of a programme for the village fair the profound created by trainee accountant has variable cost of 1500 .. And in explanation it states that variable overheads represents the cost of operating the printing press and binding machine so is this cost relevant to the decision or not? Also in performa it’s have a heading printing press depreciation according to me it shouldn’t be relevant but in explanation it says when not being used by the company the printing press is hired to outside companies for £ 7 per hour and earns a contribution of 4 an hour and unlimited demand of this facility so is this a relevant cost?

    Thanks
    Nour

    September 17, 2015 at 7:02 am #272234
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54656
    • ☆☆☆☆☆

    It is impossible for me to answer with certainty without seeing the question (and why do you have the question but not the answer?).

    However, the variable cost of 1500 would seem to be relevant – any extra cost that will be incurred is relevant.

    Depreciation itself is certainly not relevant. However the income that could be earned from using the press elsewhere is an opportunity cost and certainly is relevant.

    I do suggest that you watch the free lecture on relevant costing.

    September 28, 2015 at 9:09 am #273944
    alawi sayed
    Participant
    • Topics: 301
    • Replies: 352
    • ☆☆☆☆

    Hello Mr John ,

    When you answered Debajyoti you added the cost of the hours
    why we have to consider the cost of the hours which we have to pay anyhow

    we should include only the lost contribution
    because only we will shift the workers from the other job to the job we are concerned,

    is that ok,

    Thanks for help…

    September 28, 2015 at 11:37 am #273982
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54656
    • ☆☆☆☆☆

    No – that is wrong. I do suggest that you watch the free lecture on relevant costing.

    If we move workers from other work, then the relevant cost is the labour cost per hour plus the lost contribution per hour.

    In the free lecture I explain why in two ways. I can not type out the whole lecture here, but here is a tiny example which just might convince you.

    Suppose workers are paid $5 per hour. They are currently working on a product that takes 1 hour to make, has a selling price of $10 per unit, and materials of $1 per unit. (So a contribution of 10 – 1 – 5 = $4

    If we take the one hour for our contract, then we are still paying the labour. However, we lose the existing revenue of $10, but we save the materials of $1. So what we are losing by taking the labour away is a net $9. (Which is the same as the labour plus the lost contribution). It is a ‘trick’ the examiner often asks 🙂

    I do suggest you watch all our free lectures – they are a complete course for F5 and cover everything you need to be able to pass the exam well.

  • Author
    Posts
Viewing 8 posts - 1 through 8 (of 8 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • ACCA2025@ on Professionalism, ethical codes and the public interest – ACCA Strategic Business Leader (SBL)
  • Barlow1989 on CIMA BA2 – Accounting for Management
  • eloisabraith on FA Chapter 6 Questions Depreciation
  • azubair on Optimal pricing – equations- ACCA Performance Management (PM)
  • Rajpoot on FA Chapter 5 Questions IAS 37 – Provisions, Contingent Liabilities and Contingent Assets

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in