• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Relevant costing

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Relevant costing

  • This topic has 3 replies, 3 voices, and was last updated 3 weeks ago by LMR1006.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • February 23, 2025 at 3:49 am #715547
    ashiswar1003
    Participant
    • Topics: 30
    • Replies: 11
    • ☆

    A company is planning to bid for a one-month contract. It has sufficient spare labour and machine capacity to carry out the contract without affecting other activities. Costs associated with the contract would be as follows:

    Direct materials
    12,440
    Direct labour
    18,300
    Variable overheads
    6,020
    Depreciation
    2,000
    In addition, it is estimated that a supervisor will need to spend 50% of their time on that contract. The supervisor is paid $3,500 a month.
    What is the relevant cost of the contract?
    ??$18,460
    ??$12,440
    ??$20,210
    $14,190

    I have understand everything
    but have a doubt on supervisory cost, like they spend 50% of their time on the contract means they need to be paid half of $3500
    so $1750 supervisory cost in relevant yeah

    February 23, 2025 at 8:19 am #715548
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1480
    • ☆☆☆☆☆

    Yes it clearly states that by “ In addition, it is estimated that a supervisor will need to spend 50% of their time on that contract. The supervisor is paid $3,500 a month. “

    Supervisor’s cost 50% of 3,500 is 1,750

    April 17, 2025 at 9:10 am #716823
    shahid6543
    Participant
    • Topics: 0
    • Replies: 1
    • ☆

    QUESTION:

    I came across this past exam-style question:

    Cleverclogs is short of labour for a new one-off project needing 600 hours of labour and has choices as to where to source this. They could hire new people temporarily from an agency at a cost of $9 per hour. Alternatively, they could recruit new temporary staff at a fixed cost of advertising of $1,200 but then only pay $6 per hour for the time. They could also redirect some staff from existing work who are currently paid $7 per hour and who make sandals that generate a contribution of $3 per hour after all variable costs. Sandals are a good selling product and Cleverclogs will lose the production and the related sales whilst staff is working on the new one-off project. What is the relevant cash flow?

    The textbook gives the correct answer as $4,800, which is the least costly option (hiring new people via recruitment: $1,200 + 600×$6). That makes sense.

    However, my query is about the treatment of existing labour:

    The internal redirection method is calculated as:
    600 × ($7 + $3) = $6,000

    I don’t fully agree with this method.

    The labour is already employed and being paid $7/hour. This cost will continue whether they work on sandals or on the new project. So, the $7/hr is not an incremental cost. Therefore, the only relevant cost here should be the lost contribution of $3/hour, giving:
    600 × $3 = $1,800

    I found a previous reply by a tutor to a similar student query, which said:

    > “If labour is being diverted, then the relevant cost is always the lost contribution plus the labour cost. The labour is still going to be paid, and therefore what is lost is the sales revenue less the other variable costs, which is the same as the contribution plus the labour cost.”

    This is where I need clarification.

    We are not disputing the $4,800 answer. Our doubt is in why the $7/hr wage is treated as relevant when the labour is already being paid — it seems to us that the only opportunity cost is the forgone contribution. Can you kindly explain when we should or shouldn’t include such fixed labour cost in relevant costing?

    Thank you!

    April 17, 2025 at 9:51 pm #716831
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1480
    • ☆☆☆☆☆

    Labour is already employed and being paid, the key consideration is whether the cost is incremental or not.

    So the existing labour cost of $7 per hour is indeed a sunk cost, as it will be incurred regardless of whether the labour is redirected to the new project or continues with the current work.
    However, when labour is diverted to a new project, the relevant cost includes both the lost contribution from the existing work and the labour cost, because the labour is still being paid.
    600 hours × (7+3) = $6,000.

    The relevant cost is thus the sum of the lost contribution and the labour cost, as both contribute to the financial implications of the decision.

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • ACCA2025@ on Professionalism, ethical codes and the public interest – ACCA Strategic Business Leader (SBL)
  • Barlow1989 on CIMA BA2 – Accounting for Management
  • eloisabraith on FA Chapter 6 Questions Depreciation
  • azubair on Optimal pricing – equations- ACCA Performance Management (PM)
  • Rajpoot on FA Chapter 5 Questions IAS 37 – Provisions, Contingent Liabilities and Contingent Assets

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in