Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Relevant Costing
- This topic has 1 reply, 2 voices, and was last updated 10 months ago by LMR1006.
- AuthorPosts
- January 30, 2024 at 4:38 pm #699339
A company makes a product which requires two sequential operations (Operation 1 and Operation 2) on the same machine. The machine is fully utilised. Material costs $12 per unit.
Instead of carrying out Operation 1, the company could buy in components, for $15 per unit. This would allow production to be increased because the machine has to deal with only Operation 2.
Operation 1 takes 0.25 hours of machine time and Operation 2 takes 0.5 hours of machine time. Labour and variable overheads are incurred at a rate of $16/machine hour and the finished products sell for $30 per unit.
This question I Got from ACCA Technical Article and found the answer as follows :
Production volume – this can increase by 50% because currently each item takes 0.5 hours in Operation 2, but 0.25 hours per unit will be released by Operation 1 which now will not be needed.
Assuming output is 1,000 units, the following would occur (ignoring labour and variable overheads which we know to be constant):
Increase in revenue (50% extra could be produced) = 500 additional units x $30 = $15,000
Increase in costs (material/buy-in costs only) = (1,500 x $15) – (1,000 x $12) = $10,500
Therefore, it is worth buying in as incremental revenue exceeds incremental costs.Question is that How the Production volume increase by 50% ?
Because operation 1 takes 0.25 Hours, how they computed 50% and made incremental revenue 500 units ?January 30, 2024 at 9:39 pm #699352The production volume can increase by 50% because currently each item takes 0.5 hours in Operation 2, but 0.25 hours per unit will be released by Operation 1, which now will not be needed.
This means that for every unit that would have gone through Operation 1, the machine can now produce an additional unit in Operation 2. Therefore, the production volume can increase by 50% compared to the previous process. In the given scenario of producing 1,000 units, this translates to an additional 500 units that can be produced.
- AuthorPosts
- You must be logged in to reply to this topic.