An accountant is paid $30,000 pa and spends 2 weeks one month working on appraising project Alpha.
Why should the accountant NOT charge half his salary to the project?
A. Because his salary is sunk
b. Because his salary is not incremental.Answer is B, which I understand. However why isn’t it A as well? I thought sunk costs should be ignored?
Many thanks
May 26, 2015 at 5:01 pm #249270Sunk costs should be ignored. But they are amounts that have already been spent. The accountant will not have been paid all his salary yet! 🙂
May 26, 2015 at 5:47 pm #249300Thanks
May 27, 2015 at 6:31 am #249408Hi john just to go back to this, is the salary a committed cost then? Either way, (sunk or committed) it wouldn’t be charged to the project?
May 27, 2015 at 9:12 am #249482True – it won’t be charged to the project.