Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › relevant cost
- This topic has 2 replies, 2 voices, and was last updated 10 years ago by superwomen.
- AuthorPosts
- August 9, 2014 at 9:48 am #188848
Dear Mr John,
Q1)Optic pointer purchase a new machine, $150000 for a contract. it has an istallment cost $25000, and expected have a scrap value of $10000 in five years’ time. The machine will be depreciated on straight line basis over 5 years. What is the relevant cost of the machine for the contract?
Q2) Tau Co has just secured a new contract which requires 500 hrs of labour.
there are 400 hrs of spare labour capacity. the remaining hrs could be worked as overtime at time and a half or labour could be diverted from the production of product X. Product X earns a contribution of $4 in two labour hrs and direct labour is currently paid at a rate of $12 per normal hour. What the relevant cost of labour for the contract?August 9, 2014 at 3:35 pm #188937Q1. This is a slightly unfair question. The actual relevant cost is 175,000 now. However they will get back 10000 in 5 years, so the net relevant cost is 165,000.
But since the scrap would not be for 5 years and therefore would need discounting in order to make any decisions, I would go for a relevant cost of 175,000Q2. The relevant cost is 100 hours x (4/2 + 12) = $1400
August 10, 2014 at 2:47 am #189063Thanks 🙂
- AuthorPosts
- You must be logged in to reply to this topic.