• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

relevant cost

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › relevant cost

  • This topic has 7 replies, 3 voices, and was last updated 3 years ago by John Moffat.
Viewing 8 posts - 1 through 8 (of 8 total)
  • Author
    Posts
  • May 20, 2021 at 10:51 am #621191
    nmenon3
    Participant
    • Topics: 7
    • Replies: 51
    • ☆☆

    Greetings Sir,
    Is there any scenario of relevant cost of labour and variable overheads? how can we proceed with the same.
    Thank you in advance

    May 20, 2021 at 4:15 pm #621217
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    You can certainly be asked for the relevant cost concerning labour and concerning variable overheads. As to how you proceed it depends on the circumstances described in the question.

    If, for example, labour is being used for a new project and labour is limited (so it means losing existing production), then the relevant cost of the labour per hour is the lost contribution per hour plus the labour cost per hour. If variable overheads are charged on a labour hour basis, then the same applies to the variable overheads.

    May 21, 2021 at 3:07 am #621266
    nmenon3
    Participant
    • Topics: 7
    • Replies: 51
    • ☆☆

    1) A special job would require 50 hours of labor time. Employees are paid $10 per hour. The company permanently employs 5 workers with a working capacity of 50 hours a week. Currently, actual working hours amounts to 210 hours. The extra hours would be worked in overtime, for which the additional pay is $12.50 per hour.

    2) A special job would require 50 hours of labor time. Variable overheads are incurred at $2 per labor hour. The company permanently employs 5 workers with a working capacity of 50 hours a week. Employees are paid $10 per hour. Currently, actual working hours amounts to 210 hours. The extra hours would be worked in overtime, for which the additional pay is $12.50 per hour.

    3) A special job will require 20 hours of skilled labor. The skilled workforce is paid $15 per hour and is working at full capacity. If the special job is undertaken, the skilled labor would be taken off other work that earns a contribution of $12 per hour, after deducting the costs of the labor and variable overheads of $1.5 per hour.

    We are presented here with three different scenarios, could you please explain if there would be a difference in their workings?
    If its the same could you please explain any of the example?

    May 21, 2021 at 9:44 am #621293
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    Why are you attempting questions for which you do not have answers? You should be using a Revision Kit from one of the ACCA Approved Publishers – they have answers and explanations!

    Also, have you not watched my free lectures on relevant costing?

    1) The extra cost will be 10 hours at $12.50 per hour

    2) The labour cost is the same as in (1). In addition there are overheads for 50 hours at $2 per hour.

    3) The cost will be 20 hours at (12 + 15 + 1.50) per hour

    May 21, 2021 at 11:07 am #621312
    Sourav9271
    Participant
    • Topics: 170
    • Replies: 120
    • ☆☆☆

    In relation to your 3rd answer
    Since,
    Contribution of $12 per hour, after deducting the costs of the labor and variable overheads of $1.5 per hour.

    Sir,
    Doesn’t it mean that the actual contribution excludes $1.5 and thus if we include $1.5 then contribution will reduce rather than increase?

    May 21, 2021 at 3:12 pm #621346
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    No. As nmenon has typed it, the question says that the labour and the variable overheads have been deducted in arriving at the contribution of $12 per hour.

    The relevant cost is the lost contribution plus the labour and variable overhead costs.

    May 22, 2021 at 4:01 am #621378
    nmenon3
    Participant
    • Topics: 7
    • Replies: 51
    • ☆☆

    Thank you for the response, sir.
    Yes sir I did go through your lecture on relevant costing, had a small doubt when it came to dealing with labour and variable overhead

    May 22, 2021 at 8:25 am #621397
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    You are welcome 🙂

  • Author
    Posts
Viewing 8 posts - 1 through 8 (of 8 total)
  • The topic ‘relevant cost’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • hhys on PM Chapter 4 Questions Environmental Management Accounting
  • singhjyoti on Conceptual Framework – ACCA SBR lecture
  • John Moffat on Time Series Analysis – ACCA Management Accounting (MA)
  • azubair on Time Series Analysis – ACCA Management Accounting (MA)
  • Gowri7 on Relevant cash flows for DCF Working capital (examples 2 and 3) – ACCA Financial Management (FM)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in