• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

December 2025 ACCA Exam Results

Post comments & Instant poll

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March 2026 exams.
Get your discount code >>

Relevant cost

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Relevant cost

  • This topic has 7 replies, 4 voices, and was last updated 5 years ago by John Moffat.
Viewing 8 posts - 1 through 8 (of 8 total)
  • Author
    Posts
  • June 26, 2020 at 7:55 pm #574758
    kennigara
    Participant
    • Topics: 193
    • Replies: 250
    • ☆☆☆

    Hi Dear Tutor, I have a question.

    Q 42. VV Company has been asked to quote for a special contract. The contract requires 100 hrs of labour. However, the labourers who are each paid $15 per hour, are working at full capacity.
    There is a shortage of labour in the market. The labour required to undertake this special contract would have to be taken from another contract,Z, which currently utilises 500 hours of labour and generates $5000 worht of contributions.
    If the labour was taken from contract Z, then the whole of contract Z would have to be delayed, ans such delay would invoke a penalty fee of $1000.
    What is the relevant cost of the labour for special contract?

    why we take direct labor cost 100*15 as relevant cost?it will be paid anyway no matter of labourer will have idle time or working at full capacity.

    June 27, 2020 at 9:21 am #574781
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54812
    • ☆☆☆☆☆

    As I explain in my free lectures, if a limited resource is taken for a new contract then the relevant cost is the lost contribution from whatever the resource is currently being used for plus the cost of the resource used.

    Consider this:
    Suppose they currently make a product that has a selling price of $20, a labour cost of $5 and other variable costs (e.g. materials) of $8. So the contribution is $7.

    If the labour is taken for a new contract, then we lose the revenue of $20 but we no longer need the materials etc of $8 (we will still be paying for the labour so no saving there).

    So the net amount lost (and therefore the relevant cost) is 20 – 8 = $12. This is always the same as the lost contribution ($7) plus the cost of the labour ($5).

    June 29, 2020 at 12:18 am #574899
    tiwari.ekta1@gmail.com
    Member
    • Topics: 28
    • Replies: 45
    • ☆☆

    sir is the answer 1500+5000+1000=7500.please let me know .Thanks

    June 29, 2020 at 9:26 am #574915
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54812
    • ☆☆☆☆☆

    No, because in this specific question taking the labour will not mean losing contract Z but will just mean delaying contract Z.

    So we will still be getting the contribution from Z, but we will have to pay for more labour (because they will be working on Z and on the special contract) and we will have to pay the penalty because Z will be delayed.

    So the relevant cost is (100 x $15) + 1,000.

    June 29, 2020 at 4:28 pm #575374
    phuongmore
    Participant
    • Topics: 131
    • Replies: 128
    • ☆☆☆

    Dear sir, there is 1 question in Study text with answers that relevant cost for labour = labor cost + variable overhead+ lost contribution .It excludes direct material cost.Please help me to explain in which case relevant cost of labour includes and excludes of direct material cost. Thank you.

    June 30, 2020 at 10:05 am #575415
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54812
    • ☆☆☆☆☆

    Look at my first reply above.

    If it is labour that it in short supply then the relevant cost is the lost contribution plus the cost of the labour. If variable overheads are on a hourly basis then it includes them as well.
    Materials are irrelevant as I explain in my first reply.

    June 30, 2020 at 12:09 pm #575427
    phuongmore
    Participant
    • Topics: 131
    • Replies: 128
    • ☆☆☆

    Thank you sir.So material is never relevant cosr for labour.

    July 1, 2020 at 9:06 am #575586
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54812
    • ☆☆☆☆☆

    Not for labour – no.

  • Author
    Posts
Viewing 8 posts - 1 through 8 (of 8 total)
  • The topic ‘Relevant cost’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Sarailee95 on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • John Moffat on PM Chapter 8 Questions Cost Volume Profit Analysis
  • John Moffat on FA Chapter 8 Questions Irrecoverable Debts and Allowances
  • Payal18 on PM Chapter 8 Questions Cost Volume Profit Analysis
  • Sergiu on FA Chapter 8 Questions Irrecoverable Debts and Allowances

Copyright © 2026 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in