• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Real option to delay a project & desicion making

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › Real option to delay a project & desicion making

  • This topic has 5 replies, 2 voices, and was last updated 4 years ago by John Moffat.
Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • August 9, 2020 at 8:54 pm #579768
    fcybbm
    Member
    • Topics: 1
    • Replies: 2
    • ☆

    Hi,

    I’m confused by two examples of real option valuation related to a “delay” option.

    In the ACCA technical article, one example is about delaying the decision making on investing in a project by two years, i.e., all the cash outlays and inflows are also delayed by two years. And the value of the option calculated using the BSOP model represents “the project value with the option to delay”.

    While in Q17 of BPP revision kit, there’s also an option of delay in decision making, but this time the value of the call option represents solely “the value of the option to delay”, and project value with the option to delay is the NPV of the project without the option of delay plus the value of the call option.

    I wonder why in the first example the call option value represents the “project value with the option”, but in the second example, the call option value only represents the value of the option to delay? Is there a difference between option to delay a project (Cash flows also delayed) and option to delay decision making (cash flow not delayed but decision delayed)

    Thank you very much!

    August 10, 2020 at 7:30 am #579789
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    The technical article is correct and the BPP answer should not have added the two together.

    The confusion arose because the first time valuing this kind of option was asked in the exam, the examiner’s answer was wrong (and the examiner afterwards accepted this). It seems that BPP has not updated their answer for the error 🙁

    August 11, 2020 at 2:11 am #579886
    fcybbm
    Member
    • Topics: 1
    • Replies: 2
    • ☆

    Hi John,

    Thank you very much for your clarification.

    I’m trying to figure out a correct answer to this question: it seems that the option in question is: if project value in the future exceeds $35m, then exercise the option and go for the additional investment of $35m, if project value falls below $35m, and do not invest further. It seems that the two $7m initial investments were not considered in the option at all, and they would have been incurred no matter what.

    So can we consider the $7m investments separately to the $35m further investment and future cash inflows?

    If we completely ignore the two $7m investments:

    The option value is still unchanged at $9.127m, however, the NPV of the project is -$28.42+$18.28+$11.86+$5.93+$2.68=$10.33m. It looks like the project value with option is lower than the project value without option to delay-this gives a negative value added by the option of delay, but in theory an option couldn’t lower value of a project…

    I’m confused by the calculation results… Could you please help to see what’s wrong here? Thank you very much!

    August 11, 2020 at 10:44 am #580100
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    Sorry, I should have explained this as well (the whole question was too ‘clever’ which is what made it all a bit ridiculous and therefore would not be repeated in this form).

    What makes it different from the example in the technical article is that as you say, the 7M a year will be paid whether or not they have the option.
    If we ignore the 7M’s then without the option the PV now of the flows from 2 years onwards is $10.33M.
    With the option (still ignoring the 7M’s), then in the formula they should have used Pa as being 28.42M and not as 35M. (I know that seems inconsistent with the article, but it is because it is not the payment itself that is being delayed but the decision as to whether or not to make the payment.) If you do that, then whether or not we include the 7M’s in both calculations it does make the project with the option better than without the option 🙂

    I am sorry for not explaining this before, but again the examiner himself admitted that it did turn out to be a ridiculous question which is why the technical article appeared later.

    August 11, 2020 at 4:30 pm #580136
    fcybbm
    Member
    • Topics: 1
    • Replies: 2
    • ☆

    Hi John,

    Thank you very much for your detailed explanation. Everything suddenly makes sense 🙂

    August 12, 2020 at 9:34 am #580223
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    You are welcome 🙂

  • Author
    Posts
Viewing 6 posts - 1 through 6 (of 6 total)
  • The topic ‘Real option to delay a project & desicion making’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • hhys on PM Chapter 14 Questions More variance analysis
  • azubair on Time Series Analysis – ACCA Management Accounting (MA)
  • bizuayehuy on Interest rate risk management (1) Part 1 – ACCA (AFM) lectures
  • sokleng on FM Chapter 7 Questions – Investment appraisal – methods
  • Annabelayinloya on IFRS 16 Identifying a lease – ACCA (SBR) lectures

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in