• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

ralevant costing

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › ralevant costing

  • This topic has 1 reply, 2 voices, and was last updated 7 years ago by John Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • March 22, 2018 at 4:25 pm #443482
    toushiga
    Participant
    • Topics: 424
    • Replies: 172
    • ☆☆☆☆

    Hello Tutor, I have one question from bpp kit and its named “John Robertson”

    extract:
    “Robertson will need to be on site whilst the building work is performed. He therefore intends to do 800 hours of the skilled work himself. The remainder will be hired on an hourly basis. The current cost of skilled workers is $12 per hour. If John Robertson does not undertake the building work for this customer he can either work as a skilled worker for other builders at a rate of $12 per hour or spend the 800 hours completing urgently needed repairs to his own house. He has recently had a quotation of $12,000 for labour to repair his home. ”

    Why are the current cost of skilled labour(remainder hour) not taken into account as well as the income he can earn if the building work are not performed?

    March 22, 2018 at 4:38 pm #443486
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54720
    • ☆☆☆☆☆

    But they are taken into account in the answer.

    What you have not copied from the question is the fact that 3,200 hours of skilled labour are needed.

    The cost of his time (800 hours) is the 12,000 that he will have spend having his home repaired.
    The remaining 2,400 hours will be done by skilled labour that costs $12 per hour – a total of 28,800.

    Both the 12,000 and the 28,800 are included in the answer.

    (Which edition of the BPP Revision Kit are you using? This question is not in the current edition. If it is an old edition then be careful – the format of the exam changed and it is important that you are using a Kit that contains lots of Section A and Section B type questions (as well as Section C type questions.))

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • John Moffat on Accruals and Prepayments – ACCA Audit and Assurance (AA)
  • Rutjay on Accruals and Prepayments – ACCA Audit and Assurance (AA)
  • finance123 on Investment Appraisal – NPV, IRR – ACCA Management Accounting (MA)
  • Rashi@gupta on FA Chapter 4 Questions Accruals and Prepayments
  • natashad25 on Investment Appraisal – NPV, IRR – ACCA Management Accounting (MA)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in