sir please 1. Case A was started on 1.1.18 and met criteria on 31.8.18.
2.Case B to investigate the properties of chemical compound.
3.Case C development project completed on 30.6.18.Related cost in SOFP at opening were $290000.production & sale of new product commenced 1 sep and expected to last 36 months.
Cost for the year 31.12.18 A $34000 B cost to 31 aug $ 78870 B cost from 31 aug $ 27800 C cost to 30 june $ 19800
What amount is total expenses to SOPL? please help me sir ,I was confusing in case B & C. Hoping …