• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

Save 20% on ACCA & CIMA Books

Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>

Question on Mar/Jun 2019 PM past paper

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Question on Mar/Jun 2019 PM past paper

  • This topic has 1 reply, 2 voices, and was last updated 4 years ago by AvatarJohn Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • March 1, 2022 at 10:24 am #649547
    Avatarjb13145678
    Participant
    • Topics: 2
    • Replies: 0
    • ☆

    Dear John,

    I got a question on No.16 of 2019 PM paper.

    Volt Co generates and sells electricity. It operates two types of power station: nuclear and wind.
    The costs and output of the two types of power station are detailed below:
    Nuclear station
    A nuclear station can generate 9,000 gigawatts of electricity in each of its 40 years of useful life. Operating costs are $486m per year. Operating costs include a provision for depreciation of $175m per year to recover the $7,000m cost of building the power station.
    Each nuclear station has an estimated decommissioning cost of $12,000m at the end of its life. The decommissioning cost relates to the cost of safely disposing of spent nuclear fuel.
    Wind station
    A wind station can generate 1,750 gigawatts of electricity per year. It has a life-cycle cost of $55,000 per gigawatt and an average operating cost of $40,000 per gigawatt over its 20-year life.
    16 What is the life-cycle cost per gigawatt of the nuclear station (to the nearest $’000)?
    A $54,000 B $73,000 C $87,000 D $107,000

    The answer is C. I was wondering why building cost is not included in the lifecycle cost.

    Thank you

    March 1, 2022 at 4:02 pm #649568
    AvatarJohn Moffat
    Keymaster
    • Topics: 57
    • Replies: 54845
    • ☆☆☆☆☆

    Please do not type out full past questions because they are copyright of the ACCA and so we are not allowed to post them here. I have all past questions and so you only need to say which exam and which question 🙂

    The initial cost has effectively been included because the operating costs include deprecation and the depreciation is spreading the initial cost. To include the depreciation and the initial cost would be including the same amount twice.

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE Exams – Instant Poll

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • TEDI on IAS 16 Property, plant and equipment – Initial Recognition – CIMA F1 Financial Reporting
  • ChanNV on Framework – measurement – ACCA Financial Reporting (FR)
  • ChanNV on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • Konstantinos43 on Financial Performance Measurement – Liquidity Measures – ACCA Management Accounting (MA)
  • Hirak.5 on ACCA TX-UK FA2025 Chapter 3 Property Income and Investments – Individuals

Copyright © 2026 · Contact · Advertising · OpenLicense · About · Sitemap · Privacy Policy · Cookie settings · Comments · Log in