• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Project real option

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › Project real option

  • This topic has 12 replies, 3 voices, and was last updated 8 years ago by John Moffat.
Viewing 13 posts - 1 through 13 (of 13 total)
  • Author
    Posts
  • May 17, 2016 at 3:03 am #315390
    dragon76
    Member
    • Topics: 50
    • Replies: 77
    • ☆☆

    John,

    I often confused some below issue relevant to the this topics

    + When we need to discount Pa and Pe in BSOP model

    + To a call option, for example: if we do the project, the NPV is 50M, if we value the project with option, the value of the option shall be 60M, so which value is relevant to add the business in order to derive a business value as a whole, the NPV, the option value or both two value, pls. advise

    Thanks

    May 18, 2016 at 6:43 am #315521
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    For your first statement, the BSOP formula itself is doing the relevant discounting.

    For your second, it is the 60M that is relevant if the option exists.

    May 18, 2016 at 7:22 am #315542
    dragon76
    Member
    • Topics: 50
    • Replies: 77
    • ☆☆

    John, the i do not understand why ignore NPV 50M, could you pls. clarify

    May 18, 2016 at 7:37 am #315548
    byron1976
    Participant
    • Topics: 8
    • Replies: 37
    • ☆

    Dear Sir,
    So, I am assuming from this discussion and others about real options. Question Digunder 2007 BPP answer kit is wrong as they are adding both NPV and Options value for the whole project value

    May 18, 2016 at 8:41 am #315577
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    dragon: Because the value with the option is greater that that without it.

    byron: Yes it is wrong. The BPP answer is a copy of the examiners own answer (it was the previous examiner), but more recently the current examiner has accepted that the answer was wrong.
    The value of the option itself is the difference between the NPV without the option, and the value arrived at using the BSOP formula.

    (For the same reason my lecture is wrong – I (as with everyone) was basing it on the original examiners answer, and I do need to re-record it. Kaplan have now changed the answer in their Revision Kit, but BPP have not done so yet.)

    May 18, 2016 at 8:44 am #315581
    dragon76
    Member
    • Topics: 50
    • Replies: 77
    • ☆☆

    John, is it means that the option value of 60M including the NPV without option 50M already??

    May 18, 2016 at 8:46 am #315585
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    Correct 🙂

    May 20, 2016 at 12:10 pm #316044
    dragon76
    Member
    • Topics: 50
    • Replies: 77
    • ☆☆

    For the put option, the principle to the final is the same, John

    May 20, 2016 at 1:13 pm #316057
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    I am not sure what you mean by “the principle to the final is the same”.

    May 23, 2016 at 11:15 am #316567
    dragon76
    Member
    • Topics: 50
    • Replies: 77
    • ☆☆

    I means that in the real option : Put option, if the option value is higher than NPV without option, the higher value shall be added to business value, is it right ?

    May 23, 2016 at 12:47 pm #316584
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    The value with the option will be higher than without the option – correct 🙂

    May 24, 2016 at 7:30 am #316750
    dragon76
    Member
    • Topics: 50
    • Replies: 77
    • ☆☆

    Sorry, It must be something i still do not understand, as in BPP book, in the example Four Season invest in Spain at investment 250M in 20 years with the cash inflow 254M, while the NPV is marginal, FS be offered an option to sales the project to Government at the end of year 5 at 150M, the Risk Free 7%, standard deviation 0.3

    the value of the Put option based on BSOP is 4.7M

    in conclusion, the Project shall bring to FS is 4+4.7=8.7M, so in this case, the NPV be added to derive the final value but not take a higher one, pls. advise

    May 24, 2016 at 8:02 am #316763
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    BPP is wrong. If you read my earlier post I explain that it is because the previous examiner got his real option question wrong!
    The current examiner has now corrected it (and the technical article on real options makes it clear) but BPP has not yet changed their answers.

    The value of the option in your example is 0.7 (4.7 – 4).

  • Author
    Posts
Viewing 13 posts - 1 through 13 (of 13 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Gowri7 on Relevant cash flows for DCF Working capital (examples 2 and 3) – ACCA Financial Management (FM)
  • Govere on The use of ratios and comparisons in auditing
  • John Moffat on Relevant cash flows for DCF Working capital (examples 2 and 3) – ACCA Financial Management (FM)
  • Gowri7 on Relevant cash flows for DCF Working capital (examples 2 and 3) – ACCA Financial Management (FM)
  • Ken Garrett on The nature and structure of organisations – ACCA Paper BT

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in