• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

March 2026 ACCA Exams Results

Comments & Instant poll

Save 20% on ACCA & CIMA Books

Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>

Project Management

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA SBL Exams › Project Management

  • This topic has 2 replies, 2 voices, and was last updated 7 years ago by Avatarammar1990.
Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • May 30, 2018 at 8:02 pm #454942
    Avatarammar1990
    Member
    • Topics: 8
    • Replies: 8
    • ☆

    Heloo Ken

    I have two questions

    First, Is there any relation,connection between Gateway review and benefit realisation review especially for case studies which are focused on post implementation.

    Second, Benefits realiastion is a series of review. Can you kindly explain which reviews it is referring to? (June 2014 Q4).

    Thank you

    May 30, 2018 at 8:50 pm #454951
    AvatarKen Garrett
    Keymaster
    • Topics: 10
    • Replies: 10656
    • ☆☆☆☆☆

    I think itmis probably better not to try to reconcile the approaches. The project gateway approach is a specific approach that was championed by the UK Government, not that it helped them much with projects. Itmis not in the new SBL syllabus starting in September. There are several gateay review stages, the idea being that the project should not advance until the last stage has had a satisfactory review.

    Benefits realisation is one of the last stages of a project. Nearly all the work has been done and we have to try to make sure that the anticipated benefits are actually realised.

    May 30, 2018 at 9:36 pm #454972
    Avatarammar1990
    Member
    • Topics: 8
    • Replies: 8
    • ☆

    Thank you Ken for your quick and clear explanation. Thanks a lot!

  • Author
    Posts
Viewing 3 posts - 1 through 3 (of 3 total)
  • The topic ‘Project Management’ is closed to new replies.

Primary Sidebar

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE Exams – Instant Poll

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • oabilentatiwa on Process Technology and Quality control – CIMA E1
  • Inspire on SWOT Analysis – ACCA Strategic Business Leader (SBL)
  • Casair on Statement of cash flows – Example 1 (revision) – ACCA Financial Reporting (FR)
  • Mellytac on Sales Mix Variance – Variance analysis – ACCA Performance Management (PM)
  • newspring.kr on Group SFP – Example (PUPs) – ACCA Financial Reporting (FR)

Copyright © 2026 · Contact · Advertising · OpenLicense · About · Sitemap · Privacy Policy · Cookie settings · Comments · Log in