Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › PPE CAPITALIZATION AND CONPUTING
- This topic has 9 replies, 3 voices, and was last updated 9 years ago by MikeLittle.
- AuthorPosts
- April 15, 2015 at 10:26 pm #241454
i have three questions to ask,
1) why is it that they don’t add general overheads in the computation of ppe, my argument is, it involved in bringing the product to the present condition for its intended use.
2)A company revalued its property on 1 April 2009 to $20m ($8m for the land). The property originally cost $10m ($2m for the land) 10 years ago. The original useful economic life of 40 years is unchanged. The company’s policy is to make a transfer to realised profits in respect of excess depreciation.
How will the property be accounted for in the year ended 31 March 2010?Answer was:
Carrying value of non-current asset at revaluation date
(10,000 – ((10,000 – 2,000)/40 years x 10 years)) 8,000 Valuation 20,000 Gain on revaluation 12,000but i though i did
10,000,000/40yrs X 10yrs= 2,500,000got the second question from acca website
please help me its driving me nuts thank you.3) why is it that the excess of the depreciation should be debited from revaluation reserve and credited to retained earnings
Thank You Sir
April 16, 2015 at 5:31 pm #241540I answered this yesterday!
May 19, 2015 at 2:49 pm #247190Hi Sir,
Just a small ques from Dec 2013 Paper (Dipifr).
Why are we capitalising Borrowing costs from 1 Oct 2012 till 31st May 2013 (8 months)?
If the construction is commencing from 1st Nov 2012, should not we take it for 7 months (ie. 1st Nov 2012 to 31st May 2012)?Here is the ques:
Omega is a listed company which prepares financial statements in accordance with International Financial Reporting Standards (IFRS).
(a) On 1 October 2012, Omega purchased some land for $10 million (including legal costs of $1 million) in order to construct a new factory. Construction work commenced on 1 November 2012. Omega incurred the following costs in connection with its construction: – Preparation and levelling of the land – $300,000.
– Purchase of materials for the construction – $6·08 million in total.
– Employment costs of the construction workers – $200,000 per month.
– Overhead costs incurred directly on the construction of the factory – $100,000 per month.
– Ongoing overhead costs allocated to the construction project using Omega’s normal overhead allocation model – $50,000 per month.
– Income received during the temporary use of the factory premises as a car park during the construction period – $50,000.
– Costs of relocating employees to work at the new factory – $300,000.
– Costs of the opening ceremony on 31 July 2013 – $150,000.The factory was completed on 31 May 2013 and production began on 1 August 2013. The overall useful life of the factory building was estimated at 40 years from the date of completion. However, it is estimated that the roof will need to be replaced 20 years after the date of completion and that the cost of replacing the roof at current prices would be 30% of the total cost of the building. At the end of the 40-year period Omega has a legally enforceable obligation to demolish the factory and restore the site to its original condition. The directors estimate that the cost of demolition in 40 years’ time (based on prices prevailing at that time) will be $20 million. An annual risk adjusted discount rate which is appropriate to this project is 8%. The present value of $1 payable in 40 years’ time at an annual discount rate of 8% is 4·6 cents. The construction of the factory was partly financed by a loan of $17·5 million taken out on 1 October 2012. The loan was at an annual rate of interest of 6%. During the period 1 October 2012 to 28 February 2013 (when the loan proceeds had been fully utilised to finance the construction), Omega received investment income of $100,000 on the temporary investment of the proceeds.
We have to compute the carrying amount of Factory in SOFP of Omega at 30 Sept 2013. (14 marks)
Thanks,
SwatiMay 19, 2015 at 6:21 pm #247227A qualifying loan is a loan borrowed to finance the construction, ACQUISITION or production of a qualifying asset
Is that enough?
May 20, 2015 at 4:11 pm #247412Yes, thanks.
So capitalisation starts from 01 Oct 2012 (when we purchased the land for construction purposes)But, there is one more thing which was bothering me. Do we also have to split this net borrowing costs into depreciable and non-depreciable elements?
Regards,
SwatiMay 20, 2015 at 8:12 pm #247472I suppose we do – I’ve never thought about this before!
May 21, 2015 at 10:54 am #247569Alright Sir, thanks for the clarification.
But when i saw the Solution in the BPP Revision Kit, they have not split the borr cost. So, I thought they might have done the error there..
Also, in another similar question (past papers), I noticed that they have done the split of borr costs..
Therefore, I got confused when to split and when not to split the borr costs..??
May 21, 2015 at 3:57 pm #247717How interesting! Is there no explanation in the BPP revision kit answers?
May 21, 2015 at 7:06 pm #247763Yes..
There is no explanation with respect to it. Also, in this particular question they have not even split the borr cost.
Regards.
May 21, 2015 at 7:13 pm #247768I would have thought (but I’m not sure, as you can probably tell!) that it would be necessary to separate the two elements, land from buildings, and allocate the borrowing to both separate parts
- AuthorPosts
- You must be logged in to reply to this topic.