Post completion Audit Forums › CIMA Forums › Post completion Audit This topic has 1 reply, 2 voices, and was last updated 6 years ago by Ken Garrett. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts May 29, 2019 at 1:26 pm #517795 sureenaMember Topics: 29Replies: 11☆ Q from Pearson Vue Post completion audit cannot be conducted until the project has reached its end Ans False But aren’t PCA’s conducted after the conclusion of a project? May 29, 2019 at 3:00 pm #517834 Ken GarrettKeymaster Topics: 10Replies: 10660☆☆☆☆☆ Seems to me its true – even if you wait three months until things settlt down, it is still after the project ends. Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In