• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exams

How was your exam? Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

Planning & Operational variances.

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Planning & Operational variances.

  • This topic has 7 replies, 3 voices, and was last updated 10 years ago by John Moffat.
Viewing 8 posts - 1 through 8 (of 8 total)
  • Author
    Posts
  • October 29, 2014 at 4:58 am #206480
    Vu
    Member
    • Topics: 5
    • Replies: 7
    • β˜†

    Hi sir,

    Can you tell me whether my answers are right or wrong for this question as I don’t have the correct answers? πŸ™‚

    “A Co. makes two products X and Y. The standard costs for each unit of X and Y is 2 kgs and 1.5 kgs at the price of $6 per kg, respectively. Production level for the month of January is:
    X: Budgeted 140,000 (units) – Actual 130,000
    Y: Budgeted 200,000 (units) – Actual 240,000

    The actual cost of material purchased was $6.2 per kg and 270,000 kgs were used to make X and 350,000 kgs were used to make Y. The company changed its design of the products at the beginning of the month and the new design requires 8% material less than previously budgeted.”

    Calculate the materials price and usage planning/operational variance for the month of January.

    And here’s what I’ve done:
    Planning:
    – Price:
    -X was $259,200 (F)
    -Y was $252,000 (F)
    – Usage:
    -X was $124,800 (A)
    -Y was $172,800 (A)
    Operational:
    – Price:
    -X was $183,600 (F)
    -Y was $238,000 (F)
    – Usage:
    -X was $184,800 (A)
    -Y was $112,800 (A).

    And finally thank you for your help. πŸ™‚

    October 29, 2014 at 9:00 am #206513
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54681
    • β˜†β˜†β˜†β˜†β˜†

    I don’t know how you have calculated your answers, but they cannot possibly be correct.

    For material X, there is no mention of the price being revised, and so the planning price variance is $0.
    The operational price variance is the extra $0.20 on each of the 270,000 kg purchased, which is $54,000 (A)

    Your operational usage variance for X is correct. However your planning usage variance cannot be correct – it can’t be adverse if they revised the design to use less material!

    (If you have the question, why do you not have the answers??)

    October 29, 2014 at 1:17 pm #206569
    Vu
    Member
    • Topics: 5
    • Replies: 7
    • β˜†

    Because it’s my homework… So I don’t have the answers. And I’m still a little bit confused about these Planning & Operational variances.

    But I wonder that if you pleased, can you show me how to figure out these variances?

    Oh, anyway thank you for your help. πŸ˜€

    October 29, 2014 at 5:35 pm #206622
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54681
    • β˜†β˜†β˜†β˜†β˜†

    Have you watched my lecture on planning and operational (because I go through the rules in the lecture)?

    November 1, 2014 at 10:46 pm #207149
    josy87
    Member
    • Topics: 173
    • Replies: 215
    • β˜†β˜†β˜†

    Sir
    Please Sir I don’t understand why the operational price variance is not nil as well as there is not revised price.

    I though the formula for operational price variance is
    (revised rate – actual rate actual) actual purchased.

    planning price variance is
    (revised rate – standard rate) actual purchased.

    I don’t if i’m confused or missing something.

    November 2, 2014 at 10:09 am #207204
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54681
    • β˜†β˜†β˜†β˜†β˜†

    The price is not revised and so the revised price is the same as the original standard price of $6.00

    So the planning variance is zero, and the operational variance is the extra $0.20.

    November 2, 2014 at 10:35 am #207214
    josy87
    Member
    • Topics: 173
    • Replies: 215
    • β˜†β˜†β˜†

    so when there is not revised price we should consider the standard price the revised price, I understand now. But Sir why not consider it the price planning variance as well?

    November 2, 2014 at 12:41 pm #207237
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54681
    • β˜†β˜†β˜†β˜†β˜†

    If there had been a revision to the original standard price then you would have been told. If you are not told, then the revised price is the same as the original standard.

  • Author
    Posts
Viewing 8 posts - 1 through 8 (of 8 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options: Β β€œRead the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • John Moffat on The financial management environment – ACCA Financial Management (FM)
  • Lekhanaa on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • wZaidhan on Sources of Finance – Islamic Finance – ACCA Financial Management (FM)
  • manahylilyas on The financial management environment – ACCA Financial Management (FM)
  • poojam on Objective of financial reporting – ACCA Financial Reporting (FR)

Copyright © 2025 Β· Support Β· Contact Β· Advertising Β· OpenLicense Β· About Β· Sitemap Β· Comments Β· Log in