Dear all,
For Material Px Variance we need to take difference from actual px and actual px @ standard cost
or
budget px and actual px @ standard cost?
hi Sarahlim,
I checked that question ,I did it like this
53000kg material should cost(*2.5)=132500
but they actually costed =136000
so adverse price variance is 3500.
its the difference between actual units at standard cost and the what it actually costed.Hope this makes sense.
Yes I did it like this also but the answer is 7500 @.@ haiz……
Omg…. i refer to the wrong pilot paper….I m so sorry 3500 is correct
thats ok r u going 4 cbe?
ya…this month
U wan to go for CBE also?
yes going for cbe hopefully end of this month..