• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

past paper question dec 2012 variance alaysis:

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › past paper question dec 2012 variance alaysis:

  • This topic has 15 replies, 6 voices, and was last updated 8 years ago by John Moffat.
Viewing 16 posts - 1 through 16 (of 16 total)
  • Author
    Posts
  • May 10, 2014 at 11:56 am #168188
    ktk89
    Member
    • Topics: 4
    • Replies: 2
    • ☆

    Truffle Co makes high quality, hand-made chocolate truffles which it sells to a local retailer. All chocolates are made
    in batches of 16, to fit the standard boxes supplied by the retailer. The standard cost of labour for each batch is $6·00
    and the standard labour time for each batch is half an hour. In November, Truffle Co had budgeted production of
    24,000 batches; actual production was only 20,500 batches. 12,000 labour hours were used to complete the work
    and there was no idle time. All workers were paid for their actual hours worked. The actual total labour cost for
    November was $136,800. The production manager at Truffle Co has no input into the budgeting process.
    At the end of October, the managing director decided to hold a meeting and offer staff the choice of either accepting
    a 5% pay cut or facing a certain number of redundancies. All staff subsequently agreed to accept the 5% pay cut
    with immediate effect.
    At the same time, the retailer requested that the truffles be made slightly softer. This change was implemented
    immediately and made the chocolates more difficult to shape. When recipe changes such as these are made, it takes
    time before the workers become used to working with the new ingredient mix, making the process 20% slower for at
    least the first month of the new operation.
    The standard costing system is only updated once a year in June and no changes are ever made to the system outside
    of this.
    Required:
    (a) Calculate the total labour rate and total labour efficiency variances for November, based on the standard cost
    provided above.

    sir in the examiner ans std price = $6/.5 = 12.
    sir i can,t understand the std price$12 of the examiner answer the examiner how to calculate the ans.

    May 10, 2014 at 5:23 pm #168253
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    I think you are actually asking about the standard rate of pay!

    Each batch takes 1/2 hour to make.
    The standard cost of labour is $6 per batch.

    So it must mean that the standard rate of pay is $12 per hour.

    (The cost per batch is 0.5 hours x $12 per hour = $6. It is just working ‘backwards’)

    May 19, 2014 at 6:06 pm #169530
    Abi
    Member
    • Topics: 26
    • Replies: 64
    • ☆☆

    Regarding this question sir,i dont understand part(b)”Analyse the total labour rate and total labour efficiency variance into component parts for PLANNING & OPERATIONAL VARIANCES but i dont understand how they got their answer because i used “ACTUAL HOURS ACTUAL RATE;ACTUAL HOURS STANDARD RATE;STANDARD HOURS STANDARD RATE.and i flexed the actual of 20,500 to the revised and budgeted but i still did not get the same answer and why did the answer use “12,000 hours” shouldnt we use 20,500 batches?because in material we use units not the hours so i dont understand and i am very confused please help me.i can do all other variance question but i cant do this one especially part (B)

    May 19, 2014 at 6:37 pm #169535
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    The problem is that there are two ways of dealing with Planning and Operational variances.
    There is the sensible way (and the way that Kaplan, BPP, OpenTuition, and the examiners article from a few year ago, do it), and there is another, not so sensible, way (the way that the examiner did her answer to Truffle).

    However, the examiner did say that both methods would get full marks – even though they give different answers.

    Best is for you to look at my answer to that question.
    You can find it here:
    https://opentuition.com/acca/f5/f5-december-2012-question-2-planning-and-operational-variances/

    May 19, 2014 at 7:16 pm #169542
    Abi
    Member
    • Topics: 26
    • Replies: 64
    • ☆☆

    Thank you so much i watched the lecture.thank god i thought i didnt understand variances anymore

    May 20, 2014 at 4:15 am #169583
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    You are welcome 🙂

    May 26, 2014 at 2:47 pm #170938
    ktk89
    Member
    • Topics: 4
    • Replies: 2
    • ☆

    thanks sir

    May 26, 2014 at 3:09 pm #170945
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    You are welcome 🙂

    May 6, 2015 at 3:21 am #244281
    san
    Member
    • Topics: 35
    • Replies: 34
    • ☆☆

    Truffle Co makes high quality, hand-made chocolate truffles which it sells to a local retailer. All chocolates are made
    in batches of 16, to fit the standard boxes supplied by the retailer. The standard cost of labour for each batch is $6·00
    and the standard labour time for each batch is half an hour. In November, Truffle Co had budgeted production of
    24,000 batches; actual production was only 20,500 batches. 12,000 labour hours were used to complete the work

    sir i dont understand what do mean by in batches of 16 do we divide 24000 batches/16
    could you tell me when to divide not to divide
    when batches are given how to understand it per batch

    May 6, 2015 at 7:51 am #244294
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    They are batches of 16. It means that if 16 chocolates fit into a box, then making one batch (like making one box) is making 16 chocolates.
    So if we make 10 batches (10 boxes) it means we will be making 160 chocolates, and so on.

    May 6, 2015 at 9:37 am #244308
    san
    Member
    • Topics: 35
    • Replies: 34
    • ☆☆

    Component 1 (Circuit board) – these are bought in and cost $4·10 each. They are bought in batches of 4,000 and
    additional delivery costs are $2,400 per batch

    is this mean 1batch (or box) fit 4000 circuit board. therefore
    $2400 is per batch and 4000 is per bactch and to calculate per unit
    2400/4000batches

    is it correct sir?

    May 6, 2015 at 2:31 pm #244347
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    Yes – that is correct 🙂

    February 15, 2016 at 4:31 pm #300591
    raza jawaid
    Member
    • Topics: 0
    • Replies: 1
    • ☆

    help me

    February 15, 2016 at 4:34 pm #300592
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    Well it would help if you were to say what you needed help with!

    Presumably variances since you have posted this under a question about Paper F5 variances?

    February 9, 2017 at 8:15 am #371722
    smita8696
    Member
    • Topics: 0
    • Replies: 1
    • ☆

    hi
    the vailable papers on acca website is until june 2013 only sir can you please advice me how to get the dec 2012
    thank u

    February 9, 2017 at 3:27 pm #371766
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    Most of them are still on the ACCA website but are hidden. If you use Google to search for the relevant exam then you should be able to find it.

    However, you can find relevant past questions if you buy a Revision Kit from one of the ACCA approved publishers. It really it vital that you do buy one because the contain lots of exam standard questions (and in the new exam format) and practice is essential if you are to pass the exam. Just attempting past questions is not enough.

  • Author
    Posts
Viewing 16 posts - 1 through 16 (of 16 total)
  • The topic ‘past paper question dec 2012 variance alaysis:’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • barbjohn on Equity Law, Ratio Decidendi – ACCA LW Global
  • Kakui on Equity Law, Ratio Decidendi – ACCA LW Global
  • Nicholas1239798 on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • Starmoon123 on Strategy formulation (Part 2) – ACCA (AFM) lectures
  • nosiphoceliwedlamini@gmail.com on Revenue – Example 5 (profitable contracts) – ACCA Financial Reporting (FR)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in