• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

Save 20% on ACCA & CIMA Books

Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>

P5 -December 2012 – Rolling Budget – Question 2-b

Forums › ACCA Forums › ACCA APM Advanced Performance Management Forums › P5 -December 2012 – Rolling Budget – Question 2-b

  • This topic has 2 replies, 2 voices, and was last updated 10 years ago by AvatarMinhaj.
Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • May 30, 2015 at 3:33 pm #250648
    Avatardeepmaharaj
    Member
    • Topics: 58
    • Replies: 32
    • ☆☆

    Dear Sir,

    My presentation for the Rolling Budget is as under,

    Current Year Next Year
    Q1 Budget – Q1 Actual – Q2 Budget – Q3 Budget – Q4 Budget- Total Q1

    This format does not match with ACCA Solved answers. Kindly advise whether this format is acceptable.
    ACCA Solved answer has done Total of Q1 Actual + Q2 Budget + Q3 Budget + Q4 Budget
    While I have done total of Budget (Q1 + Q2 + Q3+Q4)- Which one is correct way of presentation !

    Kindly advise

    Deep

    May 30, 2015 at 6:42 pm #250724
    Avatardeepmaharaj
    Member
    • Topics: 58
    • Replies: 32
    • ☆☆

    In continuation of the above, my purpose of asking this is in case of Rolling budget is that whether after Q1 stage whether actual Q1 replaces Q1 budget drafted earlier.

    June 1, 2015 at 8:24 am #251209
    AvatarMinhaj
    Member
    • Topics: 1
    • Replies: 1
    • ☆

    you can do it in this way but you will have to write a lot in this presentation….i think saving time will be better so go for examiner’s style …..secondly the actual results replace the budgets . you are right about that…..in question the actual results of Q1 were available and they became the base of the budget…after Q2 end their results will be available and they will become the base i.e. you will inflate Q2 actual results by lets say 3% , if the growth rate predicted is 3% even after Q2

  • Author
    Posts
Viewing 3 posts - 1 through 3 (of 3 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE Exams – Instant Poll

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • TEDI on IAS 16 Property, plant and equipment – Initial Recognition – CIMA F1 Financial Reporting
  • ChanNV on Framework – measurement – ACCA Financial Reporting (FR)
  • ChanNV on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • Konstantinos43 on Financial Performance Measurement – Liquidity Measures – ACCA Management Accounting (MA)
  • Hirak.5 on ACCA TX-UK FA2025 Chapter 3 Property Income and Investments – Individuals

Copyright © 2026 · Contact · Advertising · OpenLicense · About · Sitemap · Privacy Policy · Cookie settings · Comments · Log in