- This topic has 6 replies, 4 voices, and was last updated 11 years ago by .
Viewing 7 posts - 1 through 7 (of 7 total)
Viewing 7 posts - 1 through 7 (of 7 total)
- You must be logged in to reply to this topic.
Interactive BPP books for September 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FM Exams › OT Mock
PQR has a demand of 7500 units per month. Each unit costs $5, ordering cost is $100 per order and the Holding cost is 10% of the purchase price per year. There is a lead time of 30 days between placing the order and receiving delivery. If they order Economic Order Quantity each time, at what level of inventory should a new order be placed ( to the nearest unit).
6000 units ?
re -order level should be enough to sustain the business through the 30 days waiting time (lead time).
30 days = one month.
and we need 7,500 units per month. so answer is 7,500 units
I actually got the question from one of the OT F9 mock exams, and the answer was 7397 units. how they arrived at the answer is what I don’t know. I will appreciate if anyone can work it out, pls
Patrick: 30 days does not equal one month. Some months have 31 days 🙂
Olaniyl: Patrick was almost correct. There are 365 days in a year, and so to have enough to last 30 days they need to order when they have 30/365 x (12 x 7500) = 7397
(and before anyone says that some years have 366 days, in the exam you always assume 365 unless told different 🙂 🙂 )
Thank you sir.
You are welcome 🙂
