Kindly help with a detailed solution to this question
Able Ltd is considering a new project with details below
Initial cost $300,000 Expected life 5yrs Estimated scrap value $20,000 Additional revenue from the project – $120,000 per year Incremental cost of the project $30,000 per year Cost of capital is 10%
a. Calculate the net present value b. The IRR for the project