Forums › ACCA Forums › ACCA PM Performance Management Forums › Need solution
- This topic has 16 replies, 3 voices, and was last updated 3 hours ago by mrjonbain.
- AuthorPosts
- May 20, 2024 at 7:28 pm #705739
A business is considering expanding its product range to include a more upmarket version of its tablet PC. The labour required to make the tablet will come from two types of people, programmers and engineers.
Programmers will be needed for 2,400 hours. There are 10 programmers working for the business in contracts demanding 40 hours work per week for 48 weeks. The business feels that 95% utilisation is acceptable and presently the programmers are operating at 93%. Extra programmers are available from an agency at an hourly cost of $35/hr.
The engineers are fully utilised, and in short supply. The only way to source the 200 hours needed to set up the production line is to divert existing engineers from another product. Production of this other product will be delayed, meaning a penalty clause in a customer contract will be triggered costing $4,000. Additionally, the engineers are paid $20/hr and the contribution earned on the delayed products is $8,200.
What is the total relevant cash flow for the programmers and the engineers for this project?
A $88,000
B $74,560
C $96,200
D $82,760May 20, 2024 at 8:21 pm #705745It is implied from the question that hours can be found for the project from internal programmers by increasing their utilisation levels fom 93% to 95%.
May 20, 2024 at 8:23 pm #705746Beyond this the remaining hours need to be provided by agency at agency cost for programmers.
May 20, 2024 at 8:25 pm #705747In terms of the engineers the relevant costs are the lost contribution and the penalty clause that will be triggered.
May 20, 2024 at 8:28 pm #705748Increased agency utilisation of programmers
Currently (10 x 40 x 48)×0.93=17856 hours.
May 20, 2024 at 8:30 pm #705749Increase programmers utilisation to 95%
(10 x 40 x 48) x 0.95 =18240 hours.
May 20, 2024 at 8:32 pm #705750Hours available through increased utilisation = 18240-17856=384 hours extra available for project.
May 20, 2024 at 8:35 pm #7057512400 hours – 384 hours= 2016 hours needed by agency programmers.
2016 x $35= $70560
May 20, 2024 at 8:37 pm #705752Engineer costs = penalty costs plus lost contribution cost.
Penalty $4000
Lost contribution =$8200Total=$12200
May 20, 2024 at 8:39 pm #705753Total relevant cost=$70560 +$12200=$82760.
May 20, 2024 at 8:40 pm #705754Welcome to the Opentuition forums. Hope the above helps.
October 27, 2024 at 5:20 pm #712882Why did you not include $20/ hour of engineer?
October 31, 2024 at 1:01 am #712930plss help!!!!
October 31, 2024 at 12:37 pm #712937I didn’t include it as it would be paid anyway. It’s therefore not a relevant cost.
October 31, 2024 at 12:40 pm #712938Only costs and revenues impacted by the decision at hand should be considered relevant.
November 4, 2024 at 7:14 pm #713020Thank u
November 5, 2024 at 5:00 am #713026You are welcome.
- AuthorPosts
- You must be logged in to reply to this topic.