Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › Mock Question
- This topic has 3 replies, 3 voices, and was last updated 2 years ago by John Moffat.
- AuthorPosts
- January 27, 2022 at 10:47 am #647589
Question 1:
The following information is available for two projects. Only one project can be undertaken.Project A
Project B
Internal rate of return (IRR)
16%
17%
Discounted payback period
3.6 years
4.1 years
Net present value (NPV)
$18,300
$16,900
Which TWO of the following statements are true?
At a cost of capital of 17% project B would have a zero NPV
Ranking the projects based on discounted payback period would make project B seem more favourable
Project A should be accepted because it has the higher NPV
Project B should be accepted because it has the higher IRR
I am not confirm about answer.
I did 1 and 3 while other did 1 and 4. Can you help me out how 4th statement is better than 3rd.Question 2:
Which TWO of the following statements about cost control and cost reduction are true?Cost control is concerned with regulating the costs of operating a business
Cost reduction is a planned approach to reducing expenditure
Cost control starts with the assumption that current cost levels are too high
Cost reduction aims to reduce costs to budget level
Answer is 1 and 2. I did 2 and 3. How can we control a cost if we do not decide that is it higher than budgeted or standards?
Please explain why 1 is correct and 3 is incorrect.Thank you in advance Professor.
January 27, 2022 at 5:11 pm #647610Q1 I do not know in which mock exam you found this question, but as you have typed it then the answer is without doubt 1 and 3 (4 is certainly not true).
Q2 Cost control does not start with the assumption that cost levels are too high. It is trying to control them in the sense of not letting them get higher than they need be.
January 28, 2022 at 6:02 am #647631John, 4th can be correct if we have cost of capital given?
January 28, 2022 at 8:08 am #647635No. The best project is the one with the highest NPV whatever the cost of capital is. We do not need to know the cost of capital in this question because we are given the NPV’s. It is not valid to compare IRR’s when choosing between projects as I explain in my free lectures.
- AuthorPosts
- You must be logged in to reply to this topic.