Mock Exam – Throughput queryForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Mock Exam – Throughput queryThis topic has 1 reply, 2 voices, and was last updated 9 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts May 30, 2015 at 10:26 am #250494 marcie157MemberTopics: 4Replies: 14☆Throughput Q:Co makes 2 products: X and Y. X Y SP 50 32 Material 10 6 Labour 20 15 Assembly time 20min 15min Max demand 1500 units 1000unitsTotal assembly time is limited to 600hrs. Using throughput, how many units Y should produce?First contribution:X: 50-10=40/0.3hrs=133.3, so X FIRST Y: 32-6=26/0.25hrs=104, Y SECONDX: 1500u*0.3=450hrs Y: 600u*0.25=150hrsWhere am I getting wrong, as my answer of 600units does not match any of the mock exam? May 30, 2015 at 2:18 pm #250546 John MoffatKeymasterTopics: 57Replies: 54636☆☆☆☆☆You have asked this twice and I have already answered you elsewhere.You are showing the time for X as being 0.3 hours, but it is not.20 minutes is 1/3 hour – not 0.3 hours.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In