- This topic has 3 replies, 2 voices, and was last updated 5 years ago by .
Viewing 4 posts - 1 through 4 (of 4 total)
Viewing 4 posts - 1 through 4 (of 4 total)
- The topic ‘Mock Exam Section B Q31’ is closed to new replies.
Interactive BPP books for September 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › Mock Exam Section B Q31
Hi John
My issue is with regards to Mock Exam Section B Q31 :
Able Ltd is considering a new project for which the following information is available:
Expected life 5 years Estimated scrap value $20,000 Additional revenue from the project $120,000 per year Incremental costs from the project $30,000 Cost of capital 10%
I have seen your following reply (which i couldn’t reply to it, hence a new topic)
“The scrap is an inflow of 20,000 in 5 years time, so discount this using the present value discount factor for 5 years at 10%.
The net cash inflow each year is 120,000 – 20,000 = 90,000 per year for 5 years, so discount this using the annuity factor for 5 years at 10%.”
Where I got confused:
When I discount 90k for 5 years and additional 20k (scrap value) at Y5 at 10% by using the discount factor instead of annuity, I get a different total.
This is what I did and failed in this question:
Y1 90000 x 0.909 = 81,810
Y2 90000 x 0.826 = 74,340
Y3 90000 x 0.751 = 67,590
Y4 90000 x 0.683 = 61,470
Y5 (90000 + 20000) x 0.621 = 68,310
TOTAL = 353,520
NPV = 353,520 – 300,000 = 53,520
This is the answer:
Y1-Y5 90,000 x 3.791 = 341,190
Y5 20000 x 0.621 = 12,420
TOTAL = 353,610
NPV = 353,610 – 300,000 = 53,610
Apologies if I am missing a very obvious error of mine. Really appreciate if you could clear this up for me.
Thanks
Regards
Mia
The difference is simply due to rounding because of the tables being rounded to 3 decimal places.
You will not be penalised for rounding the the real exam (a question like this would ask for the answer to the nearest $’thousand.
that’s great, thank you for a quick response 🙂
You are welcome 🙂
