- This topic has 3 replies, 2 voices, and was last updated 5 years ago by .
Viewing 4 posts - 1 through 4 (of 4 total)
Viewing 4 posts - 1 through 4 (of 4 total)
- The topic ‘MOCK EXAM 1 in BPP num 21.’ is closed to new replies.
Interactive BPP books for September 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › MOCK EXAM 1 in BPP num 21.
Hello sir, I’m unable to understand this num 21 on page 302.
Pls explain.
From the flexible budgets given in the question, we can tell that the material costs are variable because they are $4 per unit at each of the three levels.
Similarly the labour costs are variable because they are $5.50 per unit at each of the three levels.
It is also obvious that the total fixed costs really are fixed and will be $750,000 in total at all levels.
If they operate at 80% capacity then they will be producing 80% x 262,500 = 210,000 units.
Finally, they need one supervisor for every extra 50,000 units. For 200,000 units they would need 4 supervisors and therefore for the production of 210,000 they will need 5 supervisors (they obviously cannot emply a fraction of a supervisor 🙂 ). Therefore there will be an extra cost of 5 x $35,000 = $175,000.
Since the know the variable costs per unit, and the total fixed costs, we can now calculate the total budgeted cost.
Thank you sir!!!
You are welcome 🙂
